Article · Milestone billing
Milestone Billing for Installation and Engineering Projects
· RoboCloud
Installation and engineering projects are usually billed in milestones. The common problem is not customers refusing to pay, but finished work that accounting never hears about, so no invoice goes out, or retention held a year ago that nobody chases. These eight points keep cash following the work that is actually done.
Eight points for milestone billing
1. Set milestones when the contract is signed
Every project with value should have a milestone schedule from the start. If one is missing, the system should flag the project instead of relying on someone remembering.
2. Separate milestone types
Deposits, progress milestones, delivery milestones and retention have different payment conditions. Typing them shows what each milestone is waiting for.
3. Tie each milestone to the task that triggers it
If milestone 2 is due when installation is complete, link it to the installation task. When the task closes, the project manager and accounting are told it is ready to bill.
4. Create the invoice from the milestone
Pull the amount and description from the milestone into the invoice without re-keying, and allow only one invoice per milestone to prevent double billing.
5. Set amounts excluding VAT and show VAT separately
Milestone amounts should exclude VAT to match profit calculations, with 7% VAT added on the customer invoice and tax invoice.
6. Handle withholding tax and retention correctly
Corporate customers often withhold tax and installation work often carries 5–10% retention, so cash received is less than the invoice total. Plan cash flow on the net amount.
7. Chase retention when it falls due
Retention is usually released after the warranty period, such as one year. Create it as its own milestone with a release date instead of a note in a notebook.
8. Warn before and after due dates
Remind before a milestone is due and mark it late automatically when unpaid, visible every morning, and let customers see their own payment schedule.
How CapyM does this
CapyM by RoboCloud keeps billing milestones on every project, typed as deposit, progress, delivery or retention. A milestone can be linked to a task; when that task closes, the project manager and accounting get an in-app and LINE alert that it is ready to bill. A draft invoice can be created straight from the milestone, once only. Set the retention percentage and release period on the project and CapyM deducts it when invoicing and creates a follow-up retention milestone. It reminds three days before a milestone is due, marks unpaid milestones late, flags projects without milestones and shows customers their payment schedule in the customer portal. From 4,900 THB/month excluding VAT, with unlimited users.
How should machine installation projects be split into milestones?
A common pattern is a deposit at contract signing, progress milestones when equipment arrives on site or installation is complete, a delivery milestone at testing and acceptance, and retention released after the warranty period. Proportions depend on each contract; what matters is tying each milestone to the task that triggers it.
What is retention and how should it be recorded?
Retention is an amount the customer holds back from each milestone, often around 5–10%, and releases after the warranty period. Revenue and VAT stay the same, but cash received is lower. Record it as a separate milestone with a release date, as CapyM does automatically when an invoice is issued.
What software reminds you to invoice when project work is finished?
Choose a system that links billing milestones to tasks in the project plan and tells accounting as soon as a task closes, such as CapyM by RoboCloud, which sends in-app and LINE alerts when a milestone is ready to bill and creates the draft invoice from it.